Theory: Approach to Criticality and Reactor Kinetics

Why Startups Are Done Slowly

When a reactor is shut down, k is well below 1 and the power is too low for the power-range instruments to see. Operators bring it to critical by withdrawing control rods (or diluting boron) in small, deliberate steps while watching the source-range count rate. The plant procedure requires them to predict where criticality will occur, the estimated critical position (ECP), and to confirm it with a 1/M plot as they go. Once critical, they add a little positive reactivity and let power rise on a slow, controlled period, limited by a startup rate limit, typically 1 decade per minute (dpm).

Subcritical Multiplication

A subcritical core with a neutron source does not shut down to zero. Each source neutron starts a chain of 1 + k + k² + … neutrons, so the neutron population, and the detector count rate, settles at a level proportional to 1/(1 − k). The subcritical multiplication M compares the count rate now with the reference count rate CR₀ taken at the start. As k approaches 1, the count rate rises steeply and 1/M falls towards zero.

Subcritical Multiplication CR = S_eff / (1 − k)     (1 − k₁) CR₁ = (1 − k₂) CR₂
k₂ = 1 − (1 − k₁) CR₁ / CR₂
M = CR / CR₀     1/M = CR₀ / CR = (1 − k)/(1 − k₀)
1/M → 0 as k → 1

The 1/M Plot and the Estimated Critical Position

Plotting 1/M against rod position gives a curve that reaches zero at criticality. A straight line through the last two points, extended to 1/M = 0, predicts the critical position. Early extrapolations are poor, because rod worth is small near the bottom of the core and the curve is not straight. Each new pair of points brings the prediction closer to the true position, and procedures forbid withdrawing more than about half the remaining distance to the predicted ECP before counting again.

Linear Extrapolation to Criticality z_c = z₂ + (z₂ − z₁) × (1/M)₂ / [ (1/M)₁ − (1/M)₂ ]
Repeat after every step; stop if the prediction moves closer than expected

Integral and Differential Rod Worth

A control rod has its greatest effect where the flux is highest, in the middle of the core. Its differential worth (pcm per step) is small at the top and bottom and largest in the middle, so its integral worth follows an S-shaped curve. The bank in this lab is worth 6000 pcm in total and the reactor has k = 0.950 (ρ = −5263 pcm) with all rods inserted.

Reactivity and Rod Worth Used in This Lab ρ = (k − 1)/k    (1 pcm = 10⁻⁵ Δk/k)
ρ(z) = −5263 + 6000 [ x − sin(2πx)/(2π) ] pcm,   x = z/228
Differential worth is greatest at mid-core

Prompt and Delayed Neutrons

About 99.35% of fission neutrons are emitted within 10⁻¹⁴ s (prompt). The other 0.65% (β ≈ 0.0065 for U-235) are emitted seconds to a minute later by fission products called delayed-neutron precursors. These few delayed neutrons make the reactor controllable: as long as the added reactivity is less than β, the chain cannot sustain itself on prompt neutrons alone, and power rises at a pace set by the precursor decay. If ρ reaches β, the reactor is prompt critical and power rises in a fraction of a second. Reactivity in reactor kinetics is often quoted in dollars: ρ($) = ρ/β.

Reactor Period, Startup Rate, and Doubling Time

A few seconds after a small step of positive reactivity, the power rises exponentially on a stable period τ, the time for power to increase by a factor of e. With one effective delayed-neutron group the period depends only on ρ. Control-room instruments display the startup rate in decades per minute, and operators often time the doubling time with a stopwatch. Measuring the period after a known rod withdrawal is a standard way to measure rod worth during startup physics testing.

Period Equations (one delayed group, small positive ρ) τ = (β − ρ) / (λρ)     ρ = β / (1 + λτ)
P(t) = P₀ e^(t/τ)     SUR = 26.06 / τ (dpm)     T_d = τ ln 2
β = 0.0065, λ = 0.08 s⁻¹

Data Used in This Lab

QuantityValueQuantityValue
k with all rods in0.950 (−5263 pcm)Total bank worth6000 pcm over 228 steps
Effective delayed-neutron fraction β0.0065 (650 pcm)Effective decay constant λ0.08 s⁻¹
Source-range count time60 sStartup rate limit (typical)1 dpm
Point of adding heatabout 1% rated powerPrompt neutron lifetime ℓ*about 10⁻⁴ s (ignored)

Values follow the DOE Fundamentals Handbook (Nuclear Physics and Reactor Theory, Module 4: Reactor Theory, Reactor Operations) and the NRC Reactor Concepts Manual. One effective delayed group with λ = 0.08 s⁻¹ is the DOE approximation for small positive reactivity; a real kinetics analysis uses six delayed groups.

Operators

Licensed operators perform the 1/M plot and ECP calculation at every startup, and stop if criticality comes earlier than predicted.

Reactor engineers

Startup physics tests measure rod worth and boron worth with a reactivity computer that applies the same period equations.

Safety limits

Startup-rate trips and limits keep the period long, so that delayed neutrons, not prompt ones, control the power rise.

Reading 1/M and Period Graphs in the Control Room

Operators plot 1/M from at least two source-range detectors. A detector close to the neutron source counts many source neutrons that have not multiplied, so its 1/M falls slowly at first and its extrapolation lands beyond the true critical position, which is not conservative. A detector farther away gives an earlier, safer estimate. The period curve, τ = (β − ρ)/(λρ), shows that the period shortens slowly at small reactivity and then collapses as ρ approaches β (one dollar, prompt criticality). A startup-rate limit is a limit on the shortest period, and therefore on the largest reactivity that may be added.

Apparatus

The plant equipment used during a reactor startup. In the simulation these are modelled for you, and the readings correspond to what each instrument would show in the control room.

Control rod bank
Rod clusters of silver-indium-cadmium or boron carbide, moved in steps by the rod drive mechanisms.
Rod drive mechanisms
Magnetic-jack drives on the vessel head step the rods in or out; the rod position indication counts steps.
BF₃ source range
Source-range detector
A BF₃ or boron-lined proportional counter outside the vessel that counts neutrons when the reactor is shut down.
Neutron source
A primary (Cf-252) or secondary (Sb-Be) source rod gives a steady neutron level so the startup is always monitored.
SUR dpm
Startup-rate meter and recorder
The intermediate-range channel displays the startup rate in decades per minute and records log power against time.
Stopwatch and 1/M log
Operators time the doubling time and plot 1/M by hand to cross-check the plant computer.

Instructions: Running the Virtual Experiment

You are the reactor operator trainee at the controls for a PWR startup. The simulation has two immersive 3D work areas and two graph work areas. The parts build from undergraduate work in Parts A to C to graduate-level analysis in the last step of Parts D and E; the level of each part is shown beside its title. In each one you operate the plant, take readings, work out the answer yourself, enter it, and press Check. Record every reading and calculation in your lab report tables (modelled in the Example Report), with a labelled screenshot of each setup. Drag in any 3D view to orbit, and scroll to zoom.

Part A: Approach to Criticality with a 1/M Plot (3D Approach to Criticality) Undergraduate
1
Open Simulation → 3D Approach to Criticality. With the bank at 0 steps, press Count 60 s. This count rate is your reference CR₀. Press Record this run.
2
Withdraw the bank to 40 steps and count again. Choose Predict: inverse multiplication 1/M, calculate 1/M = CR₀/CR, and check it. Then choose Predict: multiplication factor k, calculate k = 1 − 0.050 × CR₀/CR, and check it.
3
Choose Predict: estimated critical position. Extend a straight line through your last two 1/M points to 1/M = 0, enter the rod position, and check it. Press Record this run.
4
Repeat steps 2 and 3 at 80, 120, 140, 150, and 160 steps. Watch the 1/M plot on the control-room board and the predicted critical position move as you go. Record every count in Table A and draw your own 1/M plot.
5
Withdraw one step at a time above 160 steps and find the first position where the count rate no longer levels off. Compare it with your last prediction and explain why the early predictions were so far off.
Part B: Reactor Period, Startup Rate, and Power Rise (3D Power Ascension) Undergraduate
1
Open 3D Power Ascension. Choose Set ρ with the slider, set ρ = 100 pcm and P₀ = 1 × 10⁻³ %. Choose Predict: stable reactor period τ, calculate τ = (β − ρ)/(λρ), and check it. Then check the startup rate and the doubling time.
2
Set the prediction time to 120 s. Choose Predict: power at time t, calculate P = P₀e^(t/τ), and check it. Press Start run and compare the recorder trace and the measured doubling time with your predictions. Press Record this run.
3
Repeat for ρ = 50, 200, and 400 pcm. Record each in Table B and mark which insertions stay inside the 1 dpm startup-rate limit. Explain what happens to τ as ρ approaches β = 650 pcm.
Part C: Measuring Rod Worth by the Period Method (3D Power Ascension) Undergraduate
1
Choose Withdraw bank D 10 steps past critical (worth unknown). Press Start run and wait for the power to double. Read the measured doubling time and the startup-rate meter.
2
Choose Predict: reactivity ρ from the measured doubling time. Calculate τ = T_d/ln 2 and ρ = β/(1 + λτ) in pcm, enter it, and press Check. Record the result in Table C.
3
Divide by 10 to find the differential rod worth in pcm per step near the critical position. Explain whether this withdrawal would be allowed under a 1 dpm startup-rate limit.
Part D: Comparing 1/M Estimates from Two Detectors (Graph: 1/M Detectors) Upper undergraduateGraduate step
1
Open Graph: 1/M Detectors. Choose SR-1 and the pair 100 → 120 steps. Read the three count rates, check 1/M at the second position, then check the extrapolated critical position. Press Record this run.
2
Repeat for the pairs 130 → 140 and 140 → 145, then repeat all three pairs for SR-2. Record every run in Table D, and mark each estimate as conservative (at or before the actual critical position) or not.
3
Take a labelled screenshot of the graph. Explain why the detector close to the source gives a later, non-conservative estimate early in the approach.
4
GraduateA two-point line is sensitive to count noise. For SR-1 and SR-2 with the pairs 100 → 120 and 140 → 145, check the least-squares critical position from three points (your pair plus the logged point before it). Record the four results under Table D and compare them with the two-point estimates and the actual critical position.
Part E: Period Curve and Startup-Rate Limits (Graph: Period Curve) Upper undergraduateGraduate step
1
Open Graph: Period Curve. Set ρ = 100 pcm and the limit to 1 dpm. Check the reactivity in dollars, the stable period, and the largest reactivity allowed by the limit. Press Record this run.
2
Check and record ρ = 200 and 250 pcm at 1 dpm, 100 pcm at 0.5 dpm, and 300 and 400 pcm at 2 dpm. Record all runs in Table E and mark which settings stay within the limit.
3
Describe the shape of the curve near ρ = β and explain why startup procedures keep reactivity additions well below that point.
4
GraduateThe one-group model is a simplification. At ρ = 100, 200 and 400 pcm, check the period from the six-group inhour equation (the purple curve). Record the results under Table E, and use the curve to estimate the largest reactivity a 1 dpm limit really allows.

Simulation: Approach to Criticality, Power Ascension, and Kinetics Graphs

Reactor Startup and Kinetics Virtual LabSet up the equipment, work out your answer, then Check

The reactor is shut down with all rods in (k = 0.950, found from the shutdown margin calculation). A neutron source keeps the source-range detector counting. Withdraw the control bank in steps, count for 60 s at each position, and watch the count rate climb as k approaches 1. Part A uses this work area.

About this work area: The reactor has a control rod bank that you withdraw in steps from 0 (fully inserted) to 228 (fully withdrawn). A source-range detector outside the vessel counts neutrons for 60 seconds at a time. The Readings panel gives the rod position, the count, the count rate, the reference count rate, and the extrapolated critical position from your last two counts, and every result is announced.

Setup

Count once at 0 steps first: that count is your reference count rate CR₀. Withdraw in smaller steps as the count rate climbs.

Readings

Bank position—
Counts in 60 s—
Count rate CR (cps)—
Reference CR₀ at 0 steps (cps)—
Previous count—
Status—

k at 0 steps is 0.950. The count rate is source-limited: CR = S_eff / (1 − k).

Work it out, then check

Table A: your approach-to-criticality record
Bank (steps)Counts (60 s)CR (cps)1/MkExtrapolated critical position (steps)

The reactor is now just critical at a low power. Add positive reactivity, start the stopwatch, and watch the log-power recorder. Power rises on a stable period after a few seconds. Part B and Part C use this work area.

About this work area: The power ascension area has a log-power recorder, a startup-rate meter, and a stopwatch. You choose the reactivity added and the starting power, then start the run. The Readings panel reports the elapsed time, the power, the startup rate, and the measured doubling time, and the run is announced when the power doubles and when it reaches the point of adding heat.

Setup

Readings

Reactivity added—
Elapsed time—
Power now (% rated)—
Startup rate meter (dpm)—
Measured doubling time—
Status—

Delayed-neutron data (one effective group): β_eff = 0.0065 (650 pcm), λ_eff = 0.08 s⁻¹. The prompt term ℓ*/ρ is under 0.1 s and is ignored.

Work it out, then check

Tables B and C: your power ascension record
Reactivity sourceρ (pcm)τ (s)SUR (dpm)T_d (s)Measured T_d (s)Within 1 dpm limit?

During a real startup the operators plot 1/M from more than one source-range detector. A detector close to the neutron source can give an estimate of the critical position that is too high, which is not conservative. Part D uses this work area.

About this work area: This graph work area plots 1/M against control rod position from a logged startup, for two source-range detectors: SR-1 far from the neutron source and SR-2 close to it. You choose the detector and the pair of rod positions to extrapolate from. The data table lists the count rates and 1/M at every position for both detectors, and every change is announced.

Setup

Readings

Reference count rate CR₀ (rods at 0)—
Count rate at the first position—
Count rate at the second position—
Rod travel between the two points—

1/M = CR₀/CR. Extrapolate the straight line through the two points to 1/M = 0. Logged training data.

Work it out, then check

Table D: your 1/M extrapolation record
DetectorPositions (steps)1/M first1/M secondExtrapolated critical positionActual critical positionConservative?

Every startup has a startup-rate limit, often 1 decade per minute. The period curve shows how sharply the period shortens as the added reactivity rises toward prompt criticality. Part E uses this work area.

About this work area: This graph work area plots the stable reactor period against the reactivity added, for one delayed-neutron group with β = 0.0065 and λ = 0.08 s⁻¹. You choose the reactivity and a startup-rate limit. The data table lists the period and startup rate at a range of reactivities, and every change is announced.

Setup

Readings

β (delayed-neutron fraction)—
λ (one-group decay constant)—
Period that matches the limit—

τ = (β − ρ)/(λρ); SUR = 26.06/τ dpm; reactivity in dollars = ρ/β.

Work it out, then check

Table E: your period-curve record
ρ (pcm)ρ ($)τ (s)SUR (dpm)Limit (dpm)Largest ρ allowed (pcm)Within limit?

This accessible version provides the same set-up, work-out, and check exercises as the 3D and graph work areas, using native controls, data tables, and screen-reader announcements.

Team Questions

Question 1. A shut-down reactor has k = 0.950 and a source-range count rate of 100 cps. After a rod withdrawal the count rate settles at 250 cps. What is the new k?
Question 2. The reference count rate is 100 cps and the count rate is now 400 cps. What is 1/M?
Question 3. During a startup, 1/M = 0.60 at 100 steps and 1/M = 0.30 at 140 steps. What is the estimated critical position by linear extrapolation, in steps?
Question 4. A critical reactor receives +100 pcm of reactivity. Using β = 0.0065 and λ = 0.08 s⁻¹, what is the stable period in seconds?
Question 5. What startup rate, in decades per minute, corresponds to the period in Question 4?
Question 6. Power starts at 1.0 × 10⁻³ % and rises on the period from Question 4. What is the power after 2.0 minutes, in units of 10⁻³ %? (e.g. 5.73)
Question 7: Challenge. After a control bank is withdrawn from the critical position, an operator times a power doubling time of 30.0 s. What reactivity did the withdrawal add, in pcm?

Example Lab Report

Sample report showing the expected format and level of detail. Use it as a guide for your own submission, and include labelled screenshots of each setup. Your counts will differ slightly from these because neutron counting is random.

Reactor Startup and Kinetics: 1/M, Rod Worth, and Reactor Period

Nuclear Engineering Technology | Section: [Your Section] | Date: [Date]

Lab Members: [Names of all members present]

Purpose

To bring a PWR to criticality using subcritical multiplication and a 1/M plot to predict the critical rod position; to calculate the stable period, startup rate, doubling time, and power rise for small reactivity insertions; to measure the worth of a control-rod withdrawal by the period method; and to use graphs to compare 1/M estimates from two detectors and to find the largest reactivity a startup-rate limit allows.

Theory

In a subcritical core with a source, CR = S_eff/(1 − k), so (1 − k₁)CR₁ = (1 − k₂)CR₂ and 1/M = CR₀/CR falls to zero at criticality. Above critical, power rises as P = P₀e^(t/τ) with τ = (β − ρ)/(λρ), SUR = 26.06/τ, and T_d = τ ln 2.

k₂ = 1 − (1 − k₁)CR₁/CR₂  ·  1/M = CR₀/CR  ·  τ = (β − ρ)/(λρ)  ·  ρ = β/(1 + λτ)

Table A: Approach to Criticality (CR₀ = 100.0 cps, k₀ = 0.950) Undergraduate

Bank (steps)Counts (60 s)CR (cps)1/MkExtrapolated critical position (steps)
06000100.01.00000.9500—
406226103.80.96370.95181102 (off scale)
807939132.30.75580.9622225.4
12015 700261.70.38220.9809160.9
14031 819530.30.18860.9906159.5
15058 400973.30.10270.9949162.0
160212 7023545.00.02820.9986163.8

Sample calculation (150 steps): 1/M = 100.0/973.3 = 0.1027; k = 1 − 0.050 × 0.1027 = 0.9949; z_c = 150 + 10 × 0.1027/(0.1886 − 0.1027) = 162.0 steps. The count rate first failed to level off at 165 steps.

Table B: Period and Startup Rate (P₀ = 1 × 10⁻³ %) Undergraduate

ρ (pcm)τ (s)SUR (dpm)T_d (s)Measured T_d (s)P at 120 s (%)Within 1 dpm?
50150.000.174103.97104.02.23 × 10⁻³yes
10068.750.37947.6547.75.73 × 10⁻³yes
20028.130.92719.4919.57.13 × 10⁻²yes
4007.813.3365.425.4reaches 1% at 54 sno

Table C: Rod Worth by the Period Method Undergraduate

InsertionMeasured T_d (s)τ = T_d/ln 2 (s)ρ = β/(1 + λτ) (pcm)Differential worth (pcm/step)SUR (dpm)
Bank D +10 steps past critical11.817.0227527.51.53 (above limit)

Table D: 1/M Extrapolations from Two Detectors (logged startup, CR₀ = 100.0 cps) Upper undergraduateGraduate step

DetectorPositions (steps)1/M first1/M secondExtrapolated critical positionActual critical positionConservative?
SR-1100 → 1200.58070.3821158.5164.3Yes
SR-1130 → 1400.28290.1886160.0164.3Yes
SR-1140 → 1450.18860.1444161.3164.3Yes
SR-2100 → 1200.73480.5531180.9164.3No
SR-2130 → 1400.44090.3173165.7164.3No
SR-2140 → 1450.31730.2523164.4164.3No

z = z₂ + (z₂ − z₁)(1/M)₂/[(1/M)₁ − (1/M)₂]. Include a screenshot of the 1/M graph with your extrapolation drawn.

Graduate step: least-squares lines through three points give 161.3 steps (SR-1, 80–100–120) and 160.5 steps (SR-1, 130–140–145); for SR-2 they give 193.2 and 165.2 steps. For SR-1 the fits moved closer to the true 164.3 steps and stayed conservative; for SR-2 the fit through older points landed even further beyond it (193.2 against 180.9 steps).

Table E: Period Curve and Startup-Rate Limits (β = 0.0065, λ = 0.08 s⁻¹) Upper undergraduateGraduate step

ρ (pcm)ρ ($)τ (s)SUR (dpm)Limit (dpm)Largest ρ allowed (pcm)Within limit?
1000.15468.750.3791210.7Yes
2000.30828.120.9271210.7Yes
2500.38520.001.3031210.7No
1000.15468.750.3790.5125.7Yes
3000.46214.581.7872318.3Yes
4000.6157.813.3362318.3No

Largest ρ = β/(1 + λτ) with τ = 26.06/SUR limit.

Graduate step: the six-group inhour equation (ℓ = 2 × 10⁻⁵ s) gives τ = 54.88 s at 100 pcm, 17.31 s at 200 pcm and 3.05 s at 400 pcm, against 68.75, 28.12 and 7.81 s from one group. A 1 dpm limit (τ = 26.06 s) is reached at about 160 pcm, not 210.7 pcm.

Discussion

The count rate rose slowly at first and then steeply as k approached 1, from 100 cps with all rods in to 3545 cps at 160 steps. The first extrapolations were far too high (1102 and 225 steps), because the bank has little worth near the bottom of the core, so 1/M changed little for the first 40 steps. Once the bank reached the middle of the core, where its differential worth is greatest, the predictions converged on 162 to 164 steps, and criticality occurred at 165 steps. This is why procedures require a new 1/M point after every withdrawal and forbid large steps towards the predicted position.

Above critical, the measured doubling times matched τ ln 2 within the stopwatch resolution. The period shortened sharply as ρ increased: 100 pcm gave a gentle 0.38 dpm, while 400 pcm gave 3.3 dpm and would breach a 1 dpm startup-rate limit. As ρ approaches β = 650 pcm the period falls towards zero and the reactor would become prompt critical. The period method gave 275 pcm for 10 steps of bank D, or 27.5 pcm per step near mid-core. That withdrawal gave 1.53 dpm, so in a real startup it would have to be made in smaller steps.

The graphs showed why operators watch more than one detector. SR-1, far from the source, always predicted criticality before it happened (158.5 to 161.3 steps against 164.3), which is conservative. SR-2, close to the source, sees mostly source neutrons that are not multiplied, so its 1/M fell slowly and its early estimate (180.9 steps) was 17 steps beyond the real critical position. Both detectors converged as the rods neared critical. The period curve showed that the period falls steeply as ρ rises: a 1 dpm limit allows about 211 pcm, a 0.5 dpm limit only 126 pcm, and the curve drops toward zero at prompt criticality (650 pcm, $1.00).

The graduate steps showed the limits of the simple methods. Fitting three points instead of two did not make the SR-2 estimate conservative; only moving closer to criticality, or relying on the detector far from the source, did that. The six-group inhour equation gave periods 20–60% shorter than one group with λ = 0.08 s⁻¹, because the short-lived precursor groups respond faster at larger insertions. A startup that relied on the one-group curve would reach a 1 dpm startup rate at about 160 pcm, roughly 50 pcm earlier than predicted, so procedures and reactivity computers use the full six-group data.

Conclusion

Subcritical multiplication and the 1/M plot predicted the critical position to within about 1 step once the bank was near mid-core. The one-group period equation linked reactivity, period, startup rate, and doubling time, and a measured doubling time gave a rod worth of 275 pcm for 10 steps.

Practice Questions

Show all work and include units.

Question 1
A reactor at k = 0.92 has a count rate of 50 cps. Boron dilution raises the count rate to 400 cps. What is the new k, and how much reactivity in pcm did the dilution add?
Hint: find k₂, then compare ρ = (k − 1)/k before and after.
Question 2
Using your Table A data, draw the 1/M plot and explain why the extrapolations from 0 to 80 steps over-predicted the critical position.
Hint: compare the slope of the integral rod worth curve near the bottom and the middle of the core.
Question 3
What reactivity, in pcm and in dollars, gives a startup rate of exactly 1 dpm?
Hint: τ = 26.06/SUR, then ρ = β/(1 + λτ); ρ($) = ρ/β.
Question 4
How long does it take power to rise from 1 × 10⁻⁴ % to the point of adding heat (1%) on a 60 s period? How many decades is that?
Hint: t = τ ln(P/P₀).
Question 5
Explain the role of delayed neutrons in reactor control, and what would happen if a reactivity insertion reached β.
Hint: compare the prompt neutron lifetime (about 10⁻⁴ s) with the average delay of the precursors.
Question 6: Challenge
A reactivity computer shows a startup rate of 0.50 dpm after a 5-step withdrawal near mid-core. Find the differential rod worth in pcm per step, and the largest single withdrawal that keeps SUR below 1 dpm.
Hint: find τ and ρ for 0.50 dpm, divide by 5, then use your answer to Question 3.